The construction of a community in Henan Province for 3 years has not been submitted to the relevant departments allegedly "airing guns"

The construction of a community in Henan Province for 3 years has not been submitted to the relevant departments allegedly "airing guns"
Diesel Generator | Diesel Generator Price / 2012-08-15

Last year, it was reported that the relevant authorities promised to solve the "three months" problem still not resolved.
Some of the owners of the out-of-house rental can't wait, find the relationship, get the key, and decorate the apartment.
Reading tips
The completion of more than three years has not passed the completion acceptance, buyers can only "look at the room sigh," Recently, Ye County, an economic housing project called "Khunan community" has become the focus of many home buyers complaints. As early as August last year, when the relevant leaders of the Housing Bureau of Ye County accepted the report from this reporter, they promised to “solve this issue within three months”. Today, one year has passed and the issue has not been resolved.
[Complaint]
After the fitness room was built for 3 years, it was difficult to stay
At noon on August 10th, the reporter once again came to the Kun'an Community on the west side of the East Ring Road in Yexian County. This is the first batch of suitable housing estates in Ye County. It covers an area of ​​40 mu and has 13 residential buildings and more than 600 housing units. From the outside, the yellow building has been completed, the road has been hardened, and the doors and windows have been installed, basically meeting the conditions for occupancy. However, there are not many households in the community, and weeds can be seen everywhere.
"More than 600 houses, currently only 50 or 60 households are staying." An owner of Building 1 said that he was eligible for affordable housing through an open shake. In 2008, he paid the room. According to the contract, the delivery date was New Year's Day 2009, and now more than three years have passed since the date of the agreed delivery. An owner of Building No. 8 said: “The residential area is built from the west to the east. The house was built on time, but it has not been accepted or submitted. Some owners who have rented and lived for long periods of time can’t wait. The trustee has to find a relationship. Took out the key and renovated it. Originally a popular project, it became an annoying project."
【Housing Authority】
No room was delivered because the high voltage wires were not removed
“At the moment, Kunming Community has not been completed and accepted.” In the morning, at the County Housing Authority, Du Zhiming, chairman of the labor union responsible for the matter, said.
Du Zhiming introduced that, on the one hand, 35kv high-voltage lines were buried underground in the community and there were potential safety hazards. On the other hand, there was a high-voltage line above the residential area. This high-voltage line was the power center of Ye County. If it was constructed, the whole county would lose power for one month. . It is also for this reason that the high-voltage line has not been able to move away. If the high-voltage lines do not move, there is a hidden danger in the community and it is impossible to make a room.
When planning for site selection, why did you choose to be near the high voltage line? The County Housing Authority stated frankly that when the construction of the Kun'an community was started, the site selection was rushed and did not take into account the surrounding factors. Since then, he has communicated with the Electric Power Bureau several times and the other party has also worked hard, but progress has been slow. At present, the Bureau is making active efforts to prepare for delivery after the district has been officially powered on. "This is within a month."
In fact, as early as August of last year, the reporter of this newspaper interviewed Ye Zhong of the Housing Authority. According to Li Zhongming, the director of the Housing Authority, the delay in putting the housing after the completion of the suitable housing had caused the County Party committee and county government to attach great importance to it and promised to Within 3 months, let the community reach the three-way standard and residents will be able to stay at the time."
[Power Supply Company]
Two months of work did not finish for 4 years
On the afternoon of August 10, Guo Junhui, who was responsible for the matter at the Yexian Electric Power Bureau, specifically brought the reporter to the site of the Kun'an community.
"This 110kv high-voltage line was built in 1981. That is to say, before the Kun'an Community, the community occupied our high-pressure corridor." Guo Junhui said that on this matter, the Power Supply Bureau and the county repeatedly visited the provincial power company. The report finalized the plan for moving. “Provincial companies specifically made large sums of money, and we also organized construction teams. However, the passage was coordinated by the county and it has not been implemented so far. Two months of work have not been done for 4 years. Only 7 have been built, and there are 5 others who are not allowed to enter the construction site. The county has spent a lot of energy and cannot solve it."
During the interview, a government official from Ye County said, “As an affordable housing project, the people’s minds project should not only be run well, but also should be implemented quickly. No matter which department, it is necessary to guarantee the construction speed and construction quality. The masses brought a resentment."
Next:Installation, use and regulation of marine diesel generator sets
Prev:Bronze statue of Dianzang Bodhisattva built 99m high in Jiuhuashan, Anhui Province

MIM Parts

custom MIM powder metal metallurgy parts,Injection molding powder metalluray MIM small metal lock parts,etc.

Mim Parts,Shaft Sleeve,Metal Injection Mim Part,Stainless Steel Mim Parts

NINGBO DAIKE INTELLIGENT TECHNOLOGY CO.,LTD , https://www.daker-hardware.com